617.556.0007 | 1.800.548.3522 | www.k-plaw.com | ©2019 KP Law, P.C.
SJC Upholds Broad Termination for Convenience Clause in Public Contracts
January 2019
In A.L. Prime Energy Consultant, Inc. v. Massachusetts Bay Transportation Authority, 479 Mass. 419 (2018), the
Massachusetts Supreme Judicial Court (“SJC”) held for the first time that a so-called “termination for convenience
clause” permitted a public entity to validly terminate a procurement contract solely in order to obtain a better
price, and without exposure to liability for breach of contract. This case was groundbreaking, and provides
opportunities for public entities, as discussed in further detail, below.
In this case, the Massachusetts Bay Transportation Authority (“MBTA”) had entered into a competitively bid fuel
supply contract with A.L. Prime Energy Consultant, Inc. (“Prime”), which contract provided in relevant part:
Termination for Convenience. The [MBTA] may, in its sole discretion, terminate all or any portion of this
Agreement or the work required hereunder, at any time for its convenience and/or for any reason by
giving written notice to the Contractor thirty (30) calendar days prior to the effective date of
termination….If the Contractor is not in default or in breach of any material term or condition of this
Agreement, the Contractor shall be paid its reasonable, proper and verifiable costs.…” [Emphasis
supplied].
Approximately one year after entering into the contract, the MBTA determined it would achieve greater cost
savings by opting into a competitively bid statewide contract with another vendor. As a result, the MBTA notified
Prime that it intended to terminate the agreement pursuant to the above-referenced clause. Prime filed suit
asserting claims based on breach of contract and the implied covenant of good faith and fair dealing.
Federal law interpreting termination for convenience clauses provides that a governmental entity may terminate
a contract for convenience so long as a governmental entity does not act in bad faith or abuse its discretion. State
precedent, in contrast, provides that “general contract principles” should be applied, including the principle that
unambiguous contract language must be construed in accordance with its plain meaning.
Prime argued, therefore, that the contract should be construed under federal law, and further that the court
should determine the MBTA terminated the contract in “bad faith” because its sole reason for termination was to
obtain a better price. The SJC rejected Prime’s argument, finding that the federal case law interpreting federal
procurement contracts was incompatible with state precedent and further that the mere reference in a contract
to federal regulations was not a sufficient basis to incorporate the federal standard for interpreting a termination
for convenience clause.