617.556.0007 | 1.800.548.3522 | www.k-plaw.com | ©2019 KP Law, P.C.
SJC Upholds Broad Termination for Convenience Clause in Public Contracts
January 2019
In A.L. Prime Energy Consultant, Inc. v. Massachusetts Bay Transportation Authority, 479 Mass. 419 (2018), the
Massachusetts Supreme Judicial Court (“SJC”) held for the first time that a so-called “termination for convenience
clause permitted a public entity to validly terminate a procurement contract solely in order to obtain a better
price, and without exposure to liability for breach of contract. This case was groundbreaking, and provides
opportunities for public entities, as discussed in further detail, below.
In this case, the Massachusetts Bay Transportation Authority (“MBTA”) had entered into a competitively bid fuel
supply contract with A.L. Prime Energy Consultant, Inc. (“Prime”), which contract provided in relevant part:
Termination for Convenience. The [MBTA] may, in its sole discretion, terminate all or any portion of this
Agreement or the work required hereunder, at any time for its convenience and/or for any reason by
giving written notice to the Contractor thirty (30) calendar days prior to the effective date of
termination….If the Contractor is not in default or in breach of any material term or condition of this
Agreement, the Contractor shall be paid its reasonable, proper and verifiable costs.…” [Emphasis
supplied].
Approximately one year after entering into the contract, the MBTA determined it would achieve greater cost
savings by opting into a competitively bid statewide contract with another vendor. As a result, the MBTA notified
Prime that it intended to terminate the agreement pursuant to the above-referenced clause. Prime filed suit
asserting claims based on breach of contract and the implied covenant of good faith and fair dealing.
Federal law interpreting termination for convenience clauses provides that a governmental entity may terminate
a contract for convenience so long as a governmental entity does not act in bad faith or abuse its discretion. State
precedent, in contrast, provides that “general contract principles” should be applied, including the principle that
unambiguous contract language must be construed in accordance with its plain meaning.
Prime argued, therefore, that the contract should be construed under federal law, and further that the court
should determine the MBTA terminated the contract in “bad faith” because its sole reason for termination was to
obtain a better price. The SJC rejected Prime’s argument, finding that the federal case law interpreting federal
procurement contracts was incompatible with state precedent and further that the mere reference in a contract
to federal regulations was not a sufficient basis to incorporate the federal standard for interpreting a termination
for convenience clause.
617.556.0007 | 1.800.548.3522 | www.k-plaw.com | ©2019 KP Law, P.C.
Here, the contract language provided that the MBTA could terminate the contract “in its sole discretion” and “for
its convenience and/or for any reason.” The SJC determined that this language was unambiguous and not subject
to interpretation in multiple ways. Moreover, because the MBTA had paid significant consideration for the fuel
and restricted its termination right so as to require advance notice and payment of all costs incurred prior to
termination, the SJC rejected arguments that the contract was “illusory” and lacked consideration.
In A.L. Prime, the MBTA exercised its right to terminate the contract for its convenience in order to opt into a
statewide fuel contract with another vendor at a lower price. Importantly, however, the decision specifically
leaves open the question whether a public entity may terminate a contract for its convenience in order to rebid a
new contract in order to obtain a lower price.
Consistent with the SJC’s decision in A.L. Prime, at a minimum, Massachusetts governmental entities may utilize
termination for convenience clauses to take advantage of cost savings available in more favorable statewide
contracts as market conditions change. However, there is the possibility that including such a clause in a contract
may result in bidders increasing prices to account for the risk of such termination. Therefore, public awarding
authorities will need to consider whether to include such a clause at all, and if so, ensure that the language is clear
and unambiguous and that the contract provides for adequate consideration if the termination for convenience
clause is invoked.
If you have any questions concerning the A.L. Prime case or any other contract or procurement issue, please
contact Attorney Thomas W. McEnaney (tmcenaney@k-plaw.com) or any member of our Contracts Practice
Group at 617.556.0007.
Disclaimer: This information is provided as a service by KP Law, P.C. This information is general in nature and does not, and is not intended to, constitute
legal advice. Neither the provision nor receipt of this information creates an attorney-client relationship with KP Law, P.C. Whether to take any action based
upon the information contained herein should be determined only after consultation with legal counsel.