there's any partial exceptions, where I'm going to reject anything, I do the receiving report by
email. You must always monitor contractors, even as you're making face payments, don't be
lulled into they've done great before, it must be okay now. You must enforce all of the
requirements of the contract You must enforce all of the requirements of the contract including
the scope of work. You have the right to inspect.
Of course, you have the right, it's your site. You can at any point reject any amount of the
work, require a correction, conditionally accept, but remember, if you reject or require
correction or conditionally accept, you're not gonna pay them till it's all done. If you do not
inspect, if you just pay, then your acceptance of the work is assumed and it's gonna be very
Difficult to correct afterwards. Contract modifications are two types, unilateral or bilateral. Uni
means one, bilateral means two. Between one signature ours and two signatures ours and
theirs, which is the preferred method, bilateral correct, I want both people to sign it. Now, if
they refuse, you have the right to issue a unilateral. Do not allow a contractor to strike that right
from your contract. In my contract form, we have a right to issue unilateral. This contractor
says, "I'm not gonna agree to that." I said, then you're not gonna get the contract. He goes,
"Well, if you got it, I need the right "to issue contract change orders to you "and you have no
right to reject." I go, no you don't. He said, "Why?" I go, 'cause it's the golden rule. I got the
gold, you want the gold, you're gonna go by my terms and conditions as written in the bid in
the contract or you're not gonna get it at all. And by the way, when this contractor got that
aggressive, the executive director afterwards says, I don't wanna award to these folks. "He's
trying to dictate to us how we're gonna do our job." And because of a different issue we
eventually did not.
Remember, change orders must be in writing, must be described the change in full, whether
there's a value or not, must make references to the specifications and drawings. You must tell
everybody the story, everything that's occurring and why it's being done. Time breakdown,
price, everything. One time I wanted to close out a contract, however, the contractor says, "I
have some claims, "I'm making claims." And he turned in a list of claims that added up to, I'm
gonna guess $33,000. Now investigating, and I have to investigate this right away, and
investigating the claims I found out that my construction administration area did several verbal
change orders without documenting them. And we ascertained that those came up to, I'm
gonna make a guess, $18,000. And we had to do it because the work was done, it was all
there, all the claim was there, work was done. We reprimanded the folks you know, warn them,
give them written warnings. But I had to pay 18,000. However, the other 15,000, I could not
find or justify. He says, "I want that money, I did that too." I said it was part of the work or
something like that. And he says, "No, I want that money "and I'm not gonna accept $18,000.
Well, we have to do this in 60 days concluded, and he did not accept it. That's fine. I issued a
complete written response to his, said what we agreed to and why, and what we did not agree
to the 15,000 and why and I sent him the checks certified mail for $18,000. And it said at the
bottom payment in full. So he was mad. He took that check, he scratched out the payment in
full and wrote "No, we're still in dispute for 15,000," and he cashed the check. Now, hold on, he
changed the check, that's fine. I now know that he is upset about the 15,000. How's he gonna
get that 15,000? Sue me, because we're done. Project's complete. Did he sue? No, would cost
him more money, and frankly, he was just trying to get money. It was all covered otherwise.
You must have in the file a modification registered for every contract, whether you've issued
any modifications or not. If you've issued no modifications, it will be blank. If you have issued
modifications, it will have them listed. Woe to you if you don't have PHA as a modification
register. Woe to you if you have one it's blank and you did modifications, 'cause you'll open up
an audit seeing what else you're hiding. Construction modifications are very problematic,